时间是不是不对呀?

NO.PZ2019011501000008

问题如下:

Beta Investment Corporation claims to comply with the GIPS standards. On 18 May, the firm received a notification of a portfolio’s termination. When should the portfolio be removed from the composite if composite returns are calculated monthly?

选项:

A.

30 April

B.

18 May

C.

31 May

解释:

A is correct.

考点:3.A Composite construction-3.A.6

解析:条款3.A.6 Terminated portfolios must be included in the historical performance of the composite up to the last full measurement period that each portfolio was under management

终结的组合必须被包含记录在Composites的历史业绩中,过去的历史业绩必须持续记录至该组合上一个完整的业绩评估周期结束为止。

18 May的last full measurement period是4月,所以在四月底,也就是4月30日把这个portfolio移除。

条款3.A.6 Terminated portfolios must be included in the historical performance of the composite up to the last full measurement period that each portfolio was under management。

按照条款应该是到最后一个完整计量周期,也就是说下一个周期才移除。题目问的是啥时候移除,也就是保留到4月底,5月底的那个周期才移除吧。

烦请帮忙解惑,谢谢!

2 个答案

伯恩_品职助教 · 2021年05月21日

嗨,爱思考的PZer你好:


同学 我知道你说的那个习题。我也做了。这个include和remove不要想象是一个时间段 要想成一个时间点。老外的思路和咱们不太一样

----------------------------------------------
就算太阳没有迎着我们而来,我们正在朝着它而去,加油!

伯恩_品职助教 · 2021年05月21日

嗨,爱思考的PZer你好:


同学首先你理解的知识点是没问题的。但是好像在翻译这块你理解错了

是要保留4月30日之前,然后问要从何时开始删除,那就从4月30日(不含)开始删除。这样理解了吗?

----------------------------------------------
努力的时光都是限量版,加油!