Kathy苏苏 · 2020年04月06日

问一道题:NO.PZ201601200500001305 第5小题 [ CFA II ]

* 问题详情,请 查看题干

问题如下:

5. Hernández’s best response to Costa’s third question is: "Because:

选项:

A.

the project will plot above the security market line."

B.

the project’s beta is greater than the company’s beta."

C.

the project’s IRR is greater than the required rate of return."

解释:

B is correct.

When a project is more or less risky than the company, project beta and not WACC should be used to establish the required rate of return for the capital project. In this case, the required rate of return is greater than the WACC, which means the project beta (risk) is greater than the company’s beta.

老师,一级知识忘了,能解释下A选项吗?谢谢。
1 个答案

Debrah_品职答疑助手 · 2020年04月08日

同学你好,SML是 CAPM模型的图像化,E(Ri) = Rf + beta*(E(Rm)-Rf),纵轴:E(Ri);横轴:贝塔。SML曲线上面的点是根据CAPM模型合理定价的资产。

如果说,这道题目中的required return就是根据CAPM模型定价得到的,那么Re应该就在SML曲线上,而不是above。

但是题目中没有说CAPM模型的任何信息,所以无法得到结论。