问一道题:NO.PZ2016072602000032

问题如下:

Your bank calculates a one-day 95% VAR for market risk, a one-year 99% VAR for operational risk, and a one-year 99% VAR for credit risk. The measures are $100 million, $500 million, and $1 billion, respectively. Operational risk is defined to include all risks that are not market risks and credit risks, and these three categories are mutually uncorrelated. The market risk VAR assumes normally distributed returns, and the bank expects to be successful to keep its market risk VAR at that level for the whole year. Your boss wants your best estimate of a firmwide VAR at the 1% level. Among the following choices, your best estimate is:

选项:

A.

$1.7 billion

B.

$1.94 billion

C.

$2.50 billion

D.

It is impossible to aggregate risks with different distributions having only this information.

解释:

C is correct. First, we convert the daily VAR at the 95% level to the same parameters as the other. With the normality assumption, this is VARMKT = $100 x (2.326/ 1.645) 252\sqrt{252} = $2,245. We then combine the three VARs by taking the square root of the sum of squares, which gives VAR =$2,2452+$5002+$10002\sqrt{\$2,245^2+\$500^2+\$1000^2} = $2,458.

题目里也没说是求一年的var还是一天的var,不是time horizon没给吗?这种以后就默认是一天的?

1 个答案

袁园_品职助教 · 2020年03月16日

题目里求的是一年的,所以先把 one-day VaR 转换成了 one-year VaR

题目里有一句话 “ The market risk VAR assumes normally distributed returns, and the bank expects to be successful to keep its market risk VAR at that level for the whole year. ” 让我们有足够的依据用解析里的方法把 daily 95% 转化成与其他两个指标同样条件的 annual 99%

  • 1

    回答
  • 1

    关注
  • 466

    浏览
相关问题

NO.PZ2016072602000032 问题如下 Your bank calculates a one-y 95% Vfor market risk, a one-ye99% Vfor operationrisk, ana one-ye99% Vfor cret risk. The measures are $100 million, $500 million, an$1 billion, respectively. Operationrisk is fineto inclu all risks thare not market risks ancret risks, anthese three categories are mutually uncorrelate The market risk Vassumes normally stributereturns, anthe bank expects to successful to keep its market risk Vthlevel for the whole year. Your boss wants your best estimate of a firmwi Vthe 1% level. Among the following choices, your best estimate is: $1.7 billion $1.94 billion $2.50 billion It is impossible to aggregate risks with fferent stributions having only this information. C is correct. First, we convert the ily Vthe 95% level to the same parameters the other. With the normality assumption, this is VARMKT = $100 x (2.326/ 1.645) 252\sqrt{252}252​ = $2,245. We then combine the three VARs taking the square root of the sum of squares, whigives V=$2,2452+$5002+$10002\sqrt{\$2,245^2+\$500^2+\$1000^2}$2,2452+$5002+$10002​ = $2,458. 如题

2024-04-16 19:17 1 · 回答

NO.PZ2016072602000032问题如下 Your bank calculates a one-y 95% Vfor market risk, a one-ye99% Vfor operationrisk, ana one-ye99% Vfor cret risk. The measures are $100 million, $500 million, an$1 billion, respectively. Operationrisk is fineto inclu all risks thare not market risks ancret risks, anthese three categories are mutually uncorrelate The market risk Vassumes normally stributereturns, anthe bank expects to successful to keep its market risk Vthlevel for the whole year. Your boss wants your best estimate of a firmwi Vthe 1% level. Among the following choices, your best estimate is: $1.7 billion $1.94 billion $2.50 billion It is impossible to aggregate risks with fferent stributions having only this information. C is correct. First, we convert the ily Vthe 95% level to the same parameters the other. With the normality assumption, this is VARMKT = $100 x (2.326/ 1.645) 252\sqrt{252}252​ = $2,245. We then combine the three VARs taking the square root of the sum of squares, whigives V=$2,2452+$5002+$10002\sqrt{\$2,245^2+\$500^2+\$1000^2}$2,2452+$5002+$10002​ = $2,458.如题。三个var直接相加不行吗?一般巴塞尔协议不也是直接相加的吗,这还是巴塞尔的缺点之一,没有考虑versification。题目中怎么看出来要平方后再开根号呢

2023-05-16 11:20 1 · 回答

NO.PZ2016072602000032 问题如下 Your bank calculates a one-y 95% Vfor market risk, a one-ye99% Vfor operationrisk, ana one-ye99% Vfor cret risk. The measures are $100 million, $500 million, an$1 billion, respectively. Operationrisk is fineto inclu all risks thare not market risks ancret risks, anthese three categories are mutually uncorrelate The market risk Vassumes normally stributereturns, anthe bank expects to successful to keep its market risk Vthlevel for the whole year. Your boss wants your best estimate of a firmwi Vthe 1% level. Among the following choices, your best estimate is: $1.7 billion $1.94 billion $2.50 billion It is impossible to aggregate risks with fferent stributions having only this information. C is correct. First, we convert the ily Vthe 95% level to the same parameters the other. With the normality assumption, this is VARMKT = $100 x (2.326/ 1.645) 252\sqrt{252}252​ = $2,245. We then combine the three VARs taking the square root of the sum of squares, whigives V=$2,2452+$5002+$10002\sqrt{\$2,245^2+\$500^2+\$1000^2}$2,2452+$5002+$10002​ = $2,458. Market VAR不是要求10天的吗?怎么是求一年的了?

2022-07-30 22:52 1 · 回答

NO.PZ2016072602000032 $1.94 billion $2.50 billion It is impossible to aggregate risks with fferent stributions having only this information. C is correct. First, we convert the ily Vthe 95% level to the same parameters the other. With the normality assumption, this is VARMKT = $100 x (2.326/ 1.645) 252\sqrt{252}252 ​ = $2,245. We then combine the three VARs taking the square root of the sum of squares, whigives V= $2,2452+$5002+$10002\sqrt{\$2,245^2+\$500^2+\$1000^2}$2,2452+$5002+$10002 ​ = $2,458.为什么这里的mr or不乘以12。5,直接相加

2021-05-11 16:41 1 · 回答