零息债券前三年不付息,其实都不知道是否有违约,如何会有违约概率。

* 问题详情,请 查看题干

NO.PZ201812310200000101

问题如下:

The market price of bond B1 is€875. The bond is:

选项:

A.

fairly valued.

B.

overvalued.

C.

undervalued.

解释:

B is correct.

The following table shows that the credit valuation adjustment (CVA) for the bond is

€36.49, the sum of the present values of expected loss. The steps taken to complete the table are as follows.

Step 1: Exposure at Date T is 1000 (1+r) 4T , where r is 3%. That is, exposure is computed by discounting the face value of the bond using the risk-free rate and the number of years until maturity.

Step 2: Recovery = Exposure × Recovery rate

Step 3: Loss given default (LGD) = Exposure – Recovery

Step 4: Probability of default (POD) on Date 1 is 1.50%, the assumed hazard rate. The probability of survival (POS) on Date 1 is 98.50%.

For subsequent dates, POD is calculated as the hazard rate multiplied by the previous date’s POS.

For example, to determine the Date 2 POD (1.4775%), the hazard rate of (1.50%) is multiplied by the Date 1 POS (98.50%).

Step 5: POS in Dates 2–4 = POS in the previous year – POD

(That is, POS in Year T= POS in year [ T– 1] – POD in Year T.)

POS can also be determined by subtracting the hazard rate from 100% and raising it to the power of the number of years:

(100% – 1.5000%)1 = 98.5000%

(100% – 1.5000%)2 = 97.0225%

(100% – 1.5000%)3 = 95.5672%

(100% – 1.5000%)4 = 94.1337%

Step 6: Expected loss = LGD × POD

Step 7: Discount factor (DF) for Date T is 1 (1+r) T , where r is 3%.

Step 8: PV of expected loss = Expected loss × DF

Value of the bond if the bond were default free would be 1,000 × DF for Date 4 = €888.49.

Fair value of the bond considering CVA = €888.49 – CVA = €888.49 – €36.49 = €852.00.

Because the market price of the bond (€875) is greater than the fair value of €852, B is correct.

A is incorrect because the market price of the bond differs from its fair value. C is incorrect because although the bond’s value if the bond were default free is greater than the market price, the bond has a risk of default, and CVA lowers its fair value to below the market price.

我直接计算exposure4

0 个答案
  • 0

    回答
  • 0

    关注
  • 2

    浏览
相关问题

NO.PZ201812310200000101 问题如下 The market priof bonis€875. The bonis: fairly value overvalue unrvalue B is correct. The following table shows ththe cret valuation austment (CVfor the bonis €36.49, the sum of the present values of expecteloss. The steps taken to complete the table are follows. Step 1: Exposure te T is 1000 (1+r) 4−T , where r is 3%. This, exposure is computescounting the favalue of the bonusing the risk-free rate anthe number of years until maturity. Step 2: Recovery = Exposure × Recovery rate Step 3: Loss given fault (LG = Exposure – Recovery Step 4: Probability of fault (PO on te 1 is 1.50%, the assumehazarrate. The probability of surviv(POS) on te 1 is 98.50%. For subsequent tes, POis calculatethe hazarrate multipliethe previous te’s POS. For example, to termine the te 2 PO(1.4775%), the hazarrate of (1.50%) is multipliethe te 1 POS (98.50%). Step 5: POS in tes 2–4 = POS in the previous ye– POD (This, POS in YeT= POS in ye[ T– 1] – POin YeT.) POS calso be terminesubtracting the hazarrate from 100% anraising it to the power of the number of years: (100% – 1.5000%)1 = 98.5000% (100% – 1.5000%)2 = 97.0225% (100% – 1.5000%)3 = 95.5672% (100% – 1.5000%)4 = 94.1337% Step 6: Expecteloss = LG× POD Step 7: scount factor () for te T is 1 (1+r) T , where r is 3%. Step 8: PV of expecteloss = Expecteloss × Value of the bonif the bonwere fault free woul1,000 × for te 4 = €888.49. Fair value of the bonconsiring CVA = €888.49 – CVA = €888.49 – €36.49 = €852.00. Because the market priof the bon(€875) is greater ththe fair value of €852, B is correct. A is incorrect because the market priof the bonffers from its fair value. C is incorrebecause although the bons value if the bonwere fault free is greater ththe market price, the bond ha risk of fault, anCVA lowers its fair value to below the market price. 我用二叉树计算的是么有高估的,不知道这样的做法错在哪里?为什么折现的时候是用3%来算?什么情况下用二叉树,什么情况用一个简单的无风险利率

2025-04-29 11:36 1 · 回答

NO.PZ201812310200000101 问题如下 The market priof bonis€875. The bonis: fairly value overvalue unrvalue B is correct. The following table shows ththe cret valuation austment (CVfor the bonis €36.49, the sum of the present values of expecteloss. The steps taken to complete the table are follows. Step 1: Exposure te T is 1000 (1+r) 4−T , where r is 3%. This, exposure is computescounting the favalue of the bonusing the risk-free rate anthe number of years until maturity. Step 2: Recovery = Exposure × Recovery rate Step 3: Loss given fault (LG = Exposure – Recovery Step 4: Probability of fault (PO on te 1 is 1.50%, the assumehazarrate. The probability of surviv(POS) on te 1 is 98.50%. For subsequent tes, POis calculatethe hazarrate multipliethe previous te’s POS. For example, to termine the te 2 PO(1.4775%), the hazarrate of (1.50%) is multipliethe te 1 POS (98.50%). Step 5: POS in tes 2–4 = POS in the previous ye– POD (This, POS in YeT= POS in ye[ T– 1] – POin YeT.) POS calso be terminesubtracting the hazarrate from 100% anraising it to the power of the number of years: (100% – 1.5000%)1 = 98.5000% (100% – 1.5000%)2 = 97.0225% (100% – 1.5000%)3 = 95.5672% (100% – 1.5000%)4 = 94.1337% Step 6: Expecteloss = LG× POD Step 7: scount factor () for te T is 1 (1+r) T , where r is 3%. Step 8: PV of expecteloss = Expecteloss × Value of the bonif the bonwere fault free woul1,000 × for te 4 = €888.49. Fair value of the bonconsiring CVA = €888.49 – CVA = €888.49 – €36.49 = €852.00. Because the market priof the bon(€875) is greater ththe fair value of €852, B is correct. A is incorrect because the market priof the bonffers from its fair value. C is incorrebecause although the bons value if the bonwere fault free is greater ththe market price, the bond ha risk of fault, anCVA lowers its fair value to below the market price. RT

2024-08-09 15:14 2 · 回答

NO.PZ201812310200000101 问题如下 The market priof bonis€875. The bonis: fairly value overvalue unrvalue B is correct. The following table shows ththe cret valuation austment (CVfor the bonis €36.49, the sum of the present values of expecteloss. The steps taken to complete the table are follows. Step 1: Exposure te T is 1000 (1+r) 4−T , where r is 3%. This, exposure is computescounting the favalue of the bonusing the risk-free rate anthe number of years until maturity. Step 2: Recovery = Exposure × Recovery rate Step 3: Loss given fault (LG = Exposure – Recovery Step 4: Probability of fault (PO on te 1 is 1.50%, the assumehazarrate. The probability of surviv(POS) on te 1 is 98.50%. For subsequent tes, POis calculatethe hazarrate multipliethe previous te’s POS. For example, to termine the te 2 PO(1.4775%), the hazarrate of (1.50%) is multipliethe te 1 POS (98.50%). Step 5: POS in tes 2–4 = POS in the previous ye– POD (This, POS in YeT= POS in ye[ T– 1] – POin YeT.) POS calso be terminesubtracting the hazarrate from 100% anraising it to the power of the number of years: (100% – 1.5000%)1 = 98.5000% (100% – 1.5000%)2 = 97.0225% (100% – 1.5000%)3 = 95.5672% (100% – 1.5000%)4 = 94.1337% Step 6: Expecteloss = LG× POD Step 7: scount factor () for te T is 1 (1+r) T , where r is 3%. Step 8: PV of expecteloss = Expecteloss × Value of the bonif the bonwere fault free woul1,000 × for te 4 = €888.49. Fair value of the bonconsiring CVA = €888.49 – CVA = €888.49 – €36.49 = €852.00. Because the market priof the bon(€875) is greater ththe fair value of €852, B is correct. A is incorrect because the market priof the bonffers from its fair value. C is incorrebecause although the bons value if the bonwere fault free is greater ththe market price, the bond ha risk of fault, anCVA lowers its fair value to below the market price. 如题

2024-05-16 09:58 2 · 回答

NO.PZ201812310200000101问题如下 The market priof bonis€875. The bonis: fairly value overvalue unrvalue B is correct. The following table shows ththe cret valuation austment (CVfor the bonis €36.49, the sum of the present values of expecteloss. The steps taken to complete the table are follows. Step 1: Exposure te T is 1000 (1+r) 4−T , where r is 3%. This, exposure is computescounting the favalue of the bonusing the risk-free rate anthe number of years until maturity. Step 2: Recovery = Exposure × Recovery rate Step 3: Loss given fault (LG = Exposure – Recovery Step 4: Probability of fault (PO on te 1 is 1.50%, the assumehazarrate. The probability of surviv(POS) on te 1 is 98.50%. For subsequent tes, POis calculatethe hazarrate multipliethe previous te’s POS. For example, to termine the te 2 PO(1.4775%), the hazarrate of (1.50%) is multipliethe te 1 POS (98.50%). Step 5: POS in tes 2–4 = POS in the previous ye– POD (This, POS in YeT= POS in ye[ T– 1] – POin YeT.) POS calso be terminesubtracting the hazarrate from 100% anraising it to the power of the number of years: (100% – 1.5000%)1 = 98.5000% (100% – 1.5000%)2 = 97.0225% (100% – 1.5000%)3 = 95.5672% (100% – 1.5000%)4 = 94.1337% Step 6: Expecteloss = LG× POD Step 7: scount factor () for te T is 1 (1+r) T , where r is 3%. Step 8: PV of expecteloss = Expecteloss × Value of the bonif the bonwere fault free woul1,000 × for te 4 = €888.49. Fair value of the bonconsiring CVA = €888.49 – CVA = €888.49 – €36.49 = €852.00. Because the market priof the bon(€875) is greater ththe fair value of €852, B is correct. A is incorrect because the market priof the bonffers from its fair value. C is incorrebecause although the bons value if the bonwere fault free is greater ththe market price, the bond ha risk of fault, anCVA lowers its fair value to below the market price. 为什么不用下面二叉树利率折线呢

2024-04-20 16:26 1 · 回答

NO.PZ201812310200000101 问题如下 The market priof bonis€875. The bonis: fairly value overvalue unrvalue B is correct. The following table shows ththe cret valuation austment (CVfor the bonis €36.49, the sum of the present values of expecteloss. The steps taken to complete the table are follows. Step 1: Exposure te T is 1000 (1+r) 4−T , where r is 3%. This, exposure is computescounting the favalue of the bonusing the risk-free rate anthe number of years until maturity. Step 2: Recovery = Exposure × Recovery rate Step 3: Loss given fault (LG = Exposure – Recovery Step 4: Probability of fault (PO on te 1 is 1.50%, the assumehazarrate. The probability of surviv(POS) on te 1 is 98.50%. For subsequent tes, POis calculatethe hazarrate multipliethe previous te’s POS. For example, to termine the te 2 PO(1.4775%), the hazarrate of (1.50%) is multipliethe te 1 POS (98.50%). Step 5: POS in tes 2–4 = POS in the previous ye– POD (This, POS in YeT= POS in ye[ T– 1] – POin YeT.) POS calso be terminesubtracting the hazarrate from 100% anraising it to the power of the number of years: (100% – 1.5000%)1 = 98.5000% (100% – 1.5000%)2 = 97.0225% (100% – 1.5000%)3 = 95.5672% (100% – 1.5000%)4 = 94.1337% Step 6: Expecteloss = LG× POD Step 7: scount factor () for te T is 1 (1+r) T , where r is 3%. Step 8: PV of expecteloss = Expecteloss × Value of the bonif the bonwere fault free woul1,000 × for te 4 = €888.49. Fair value of the bonconsiring CVA = €888.49 – CVA = €888.49 – €36.49 = €852.00. Because the market priof the bon(€875) is greater ththe fair value of €852, B is correct. A is incorrect because the market priof the bonffers from its fair value. C is incorrebecause although the bons value if the bonwere fault free is greater ththe market price, the bond ha risk of fault, anCVA lowers its fair value to below the market price. 是因为利率没有波动才用的无风险收益吗?如果利率有波动就要用表格里的?

2024-04-10 11:14 2 · 回答