Which of the following statements concerning cash-flow forecasts for projects is most likely correct?

选项:

A.include the cost of market research that was recently completed. B.ignore potential loss of revenue from existing products that could occur if project is undertaken. C.if delay all future cash flows by six months, the result would be a lower IRR and a lower NPV.

解释:

Correct Answer: C

C is correct. The forecasted timing of cash flow is an important factor affecting both projects’ IRR and NPV. In the case of delaying all future cash flows from both projects by six months, the result would be a lower IRR and a lower NPV. Given that all future cash flows are to be received six months later, their present value decreases; hence, the NPV and IRR of an entire project also decrease.

A is incorrect. The market research costs in this case are a sunk cost because the research has already been completed and therefore does not affect cash-flow estimates.

B is incorrect. Capital allocation analysis should include only incremental cash flows associated with a new investment. The loss of revenue from existing products is an incremental negative effect that should be included in the analysis.

C也不对吧,all cashflow说明invest(cash out)也delay,那么整体都delay是不会影响的。

另外A虽然是sunk cost,但也是cost,这部分不计入IRR整体收益计算吗?那这部分cost算公司的SG&A??

1 个答案

Kiko_品职助教 · 2024年10月08日

嗨,从没放弃的小努力你好:


他说的是delay all future cash flows 6个月,那就是所有未来现金流都往后推迟六个月才收到,那往前折现出来的现值一定是会受影响的。而且是降低,所以整个项目的净现值和内部收益率都会降低。

沉默成本是要忽略的。是的,算SG&A。因为调研已经完成,因此不会影响现金流估计。可以看下讲义下面的ignore

----------------------------------------------
就算太阳没有迎着我们而来,我们正在朝着它而去,加油!

  • 1

    回答
  • 0

    关注
  • 62

    浏览
相关问题

NO.PZ2023112701000047问题如下 Whiof the following statements concerning cash-flow forecasts for projects is most likely correct? A.inclu the cost of market researthwrecently completeB.ignore potentiloss of revenue from existing procts thcouloccur if projeis unrtaken.C.if lall future cash flows six months, the result woula lower IRR ana lower NPV.CorreAnswer: is correct. The forecastetiming of cash flow is important factor affecting both projects’ IRR anNPV. In the case of laying all future cash flows from both projects six months, the result woula lower IRR ana lower NPV. Given thall future cash flows are to receivesix months later, their present value creases; hence, the NPV anIRR of entire projealso crease.A is incorrect. The market researcosts in this case are a sunk cost because the researhalrea been completeantherefore es not affecash-flow estimates. B is incorrect. Capitallocation analysis shoulinclu only incrementcash flows associatewith a new investment. The loss of revenue from existing procts is incrementnegative effethshoulincluin the analysis.A项可以用公式一下吗?lay是影响分母吗

2024-01-06 16:57 1 · 回答

NO.PZ2023112701000047 问题如下 Whiof the following statements concerning cash-flow forecasts for projects is most likely correct? A.inclu the cost of market researthwrecently complete B.ignore potentiloss of revenue from existing procts thcouloccur if projeis unrtaken. C.if lall future cash flows six months, the result woula lower IRR ana lower NPV. CorreAnswer: is correct. The forecastetiming of cash flow is important factor affecting both projects’ IRR anNPV. In the case of laying all future cash flows from both projects six months, the result woula lower IRR ana lower NPV. Given thall future cash flows are to receivesix months later, their present value creases; hence, the NPV anIRR of entire projealso crease.A is incorrect. The market researcosts in this case are a sunk cost because the researhalrea been completeantherefore es not affecash-flow estimates. B is incorrect. Capitallocation analysis shoulinclu only incrementcash flows associatewith a new investment. The loss of revenue from existing procts is incrementnegative effethshoulincluin the analysis. b能一下吗,没太明白为什么

2023-12-24 09:56 1 · 回答