What's the ongoing work when an enterprise determines the risk tolerance?

选项:

A.

Assess the probability of failure in risk management.

B.

Match risk exposures consistent with risk tolerance.

C.

Analyze the environment for relevant risk drivers.

解释:

B is correct.

Once the risk tolerance is set, an enterprise can step into operational level to align the risk exposure with risk tolerance.

为了持续把控风险敞口与风险容忍度一致,应该持续评估风险管理中可能出现的失败、同时分析产生风险驱动的环境吧?


1 个答案

Kiko_品职助教 · 2024年09月05日

嗨,爱思考的PZer你好:


a选项评估风险管理中失败的概率。这是最初就应该确定的,c选项分析相关风险驱动因素的环境。这也是需要在风险容忍度之前就确定的。

----------------------------------------------
就算太阳没有迎着我们而来,我们正在朝着它而去,加油!

  • 1

    回答
  • 0

    关注
  • 77

    浏览
相关问题

NO.PZ2018070201000025问题如下What's the ongoing work when enterprise termines the risk tolerance?A.Assess the probability of failure in risk management.B.Matrisk exposures consistent with risk tolerance.C.Analyze the environment for relevant risk ivers.B is correct.Onthe risk toleranis set, enterprise cstep into operationlevel to align the risk exposure with risk tolerance.risk exposure不是发生在risk tolerance后面吗 为什么b是对的

2024-10-11 10:40 1 · 回答

NO.PZ2018070201000025 问题如下 What's the ongoing work when enterprise termines the risk tolerance? A.Assess the probability of failure in risk management. B.Matrisk exposures consistent with risk tolerance. C.Analyze the environment for relevant risk ivers. B is correct.Onthe risk toleranis set, enterprise cstep into operationlevel to align the risk exposure with risk tolerance. 请问讲义哪里提到了

2024-04-11 05:24 1 · 回答

NO.PZ2018070201000025 问题如下 What's the ongoing work when enterprise termines the risk tolerance? A.Assess the probability of failure in risk management. B.Matrisk exposures consistent with risk tolerance. C.Analyze the environment for relevant risk ivers. B is correct.Onthe risk toleranis set, enterprise cstep into operationlevel to align the risk exposure with risk tolerance. A、C是因为不符合On-going的表述吗?还是因为什么其他原因不选

2023-09-10 22:34 1 · 回答

Matrisk exposures consistent with risk tolerance. Analyze the environment for relevant risk ivers. B is correct. Onthe risk toleranis set, enterprise cstep into operationlevel to align the risk exposure with risk tolerance. 老师,这道题目说的不是在决定风险偏好时需要做的持续性工作吗?b看起来是风险政策已经出完了以后,执行层面的事情了啊

2020-09-30 23:58 2 · 回答