A项

NO.PZ2023112701000047

问题如下:

Which of the following statements concerning cash-flow forecasts for projects is most likely correct?

选项:

A.include the cost of market research that was recently completed.

B.ignore potential loss of revenue from existing products that could occur if project is undertaken.

C.if delay all future cash flows by six months, the result would be a lower IRR and a lower NPV.

解释:

Correct Answer: C

C is correct. The forecasted timing of cash flow is an important factor affecting both projects’ IRR and NPV. In the case of delaying all future cash flows from both projects by six months, the result would be a lower IRR and a lower NPV. Given that all future cash flows are to be received six months later, their present value decreases; hence, the NPV and IRR of an entire project also decrease.

A is incorrect. The market research costs in this case are a sunk cost because the research has already been completed and therefore does not affect cash-flow estimates.

B is incorrect. Capital allocation analysis should include only incremental cash flows associated with a new investment. The loss of revenue from existing products is an incremental negative effect that should be included in the analysis.

A项可以用公式解释一下吗?delay是影响分母吗

1 个答案

王琛_品职助教 · 2024年01月08日

嗨,从没放弃的小努力你好:


1

我理解同学问的是 C 选项?

根据 NPV 和 IRR 的计算公式,delay 影响的是分子的现金流

2

我在课后题讲解中介绍过一个简便算法

题目虽然假设是延迟 6 个月

但是为了咱们方便计算,可以假设是延迟 1 年,然后举个例子计算一下即可

也请参考课后题的讲解截图

----------------------------------------------
努力的时光都是限量版,加油!

  • 1

    回答
  • 0

    关注
  • 270

    浏览
相关问题

NO.PZ2023112701000047 问题如下 Whiof the following statements concerning cash-flow forecasts for projects is most likely correct? A.inclu the cost of market researthwrecently complete B.ignore potentiloss of revenue from existing procts thcouloccur if projeis unrtaken. C.if lall future cash flows six months, the result woula lower IRR ana lower NPV. CorreAnswer: is correct. The forecastetiming of cash flow is important factor affecting both projects’ IRR anNPV. In the case of laying all future cash flows from both projects six months, the result woula lower IRR ana lower NPV. Given thall future cash flows are to receivesix months later, their present value creases; hence, the NPV anIRR of entire projealso crease.A is incorrect. The market researcosts in this case are a sunk cost because the researhalrea been completeantherefore es not affecash-flow estimates. B is incorrect. Capitallocation analysis shoulinclu only incrementcash flows associatewith a new investment. The loss of revenue from existing procts is incrementnegative effethshoulincluin the analysis. C也不对吧,all cashflow说明invest(cash out)也lay,那么整体都lay是不会影响的。另外A虽然是sunk cost,但也是cost,这部分不计入IRR整体收益计算吗?那这部分cost算公司的SG A??

2024-10-02 11:03 1 · 回答

NO.PZ2023112701000047 问题如下 Whiof the following statements concerning cash-flow forecasts for projects is most likely correct? A.inclu the cost of market researthwrecently complete B.ignore potentiloss of revenue from existing procts thcouloccur if projeis unrtaken. C.if lall future cash flows six months, the result woula lower IRR ana lower NPV. CorreAnswer: is correct. The forecastetiming of cash flow is important factor affecting both projects’ IRR anNPV. In the case of laying all future cash flows from both projects six months, the result woula lower IRR ana lower NPV. Given thall future cash flows are to receivesix months later, their present value creases; hence, the NPV anIRR of entire projealso crease.A is incorrect. The market researcosts in this case are a sunk cost because the researhalrea been completeantherefore es not affecash-flow estimates. B is incorrect. Capitallocation analysis shoulinclu only incrementcash flows associatewith a new investment. The loss of revenue from existing procts is incrementnegative effethshoulincluin the analysis. b能一下吗,没太明白为什么

2023-12-24 09:56 1 · 回答