NO.PZ2023090506000015
问题如下:
Compared to going concern projects, expansion projects are most likely associated with:
选项:
A.
higher levels of uncertainty alone.
B.
increased capital requirements alone.
C.
both increased uncertainty and higher capital requirements.
解释:
C is correct because expansion projects, by their nature, introduce both increased uncertainty and significant capital demands.
These projects seek to grow the business beyond its current operations, requiring substantial investment and facing higher risks compared to maintaining existing activities.